Risinger Road

Risinger at IH 35 (1811) is about 50% complete. The new pavement transition on Risinger east of the northbound frontage road is complete. Traffic signal foundations and conduit are currently being installed. Paving is expected to be complete in January 2021 and the signal should be completed in March 2021.

 

Risinger Road from McCart to Crowley (C02239) is expected to be open for traffic in January with final completion in March. 85% of the concrete is in place, 75% of the sidewalk is in place and the traffic signal is under construction.

 

Everman Parkway

The concrete and roadway rehabilitation work on Everman Parkway is complete with the final surface course of pavement being placed by the county in early to mid-January, depending on the weather conditions. Minor work such as handrail installation will be completed within the next two weeks and any repair or punchlist work will take place in the January and February timeframe.

Completed sidewalks on Crowley Road

Sidewalks on Crowley Rd were recently completed as a part of 2018 Bond sidewalk year 1, location D.

  

Sidewalk at Altamesa and Crowley

We recently completed a sidewalk on Altamesa Blvd that ended at SW Corner of intersection of Crowley and Altamesa. A different sidewalk project ended on the  SE corner of same intersection. We have requested additional information for sidewalks at this intersection and will share updates as it is provided.